Facilities News

Universalis Centralis 

Finally the SMU Universalis Centralis (sculpture) is finally going to be placed in front of 3100 Telegraph. This project will take approximately 3-4 weeks to be completed.  Breakdown of project is as follows;

  • Week of April 15: Concrete removal and replacement. Start and finish of the week will be the loudest portions due to concrete removal and repouring;  there will be Jackhammers and other equipment operating;
  • Week of April 29: Carpentry for bench replacement, final electric work and landscape replacement;
  • Week of May 30: Installation of sculpture.  

Motion Analysis Research Center (MARC)

  • Construction to began March, 2013
  • Completion May 24, 2013
  • Furniture/equipment set up TBA
  • Set move/opening date TBA